How to Read a Virginia Solar Interconnection Approval Letter

How to Read a Virginia Solar Interconnection Approval Letter

Quick Summary

A solar interconnection approval letter is your utility's written confirmation that your system can connect to the grid, and it sets the system size, export limit and conditions you must meet. Check the project identifiers, approved capacity and export limit against your contract, then wait for written permission to operate before energizing.

  • Verify the service address and application number match your contract and utility bill.
  • Confirm the approved capacity matches your contract; DC and AC figures are not the same.
  • Check that the inverter model on the letter matches the equipment actually installed.
  • Do not energize the system until permission to operate arrives in writing.
  • Note any expiration date on the letter and request an extension before it passes.

Table of Contents

How to Read a Virginia Solar Interconnection Approval Letter

Last Updated: November 22, 2026

What a Virginia Solar Interconnection Approval Letter Covers

Your solar interconnection approval letter is the document your utility sends to confirm your system can connect to the grid. Reading it carefully helps you know exactly what you are signing off on. Read it slowly. Every field matters.

The letter usually confirms four things: your project is approved for interconnection, the system size is recorded, the export limit is set, and any conditions must be met before you switch on. Think of it as the utility's written permission to connect, with rules attached.

  • Project and account identifiers
  • Approved system size and equipment
  • Export limit and net metering terms
  • Conditions and next steps

Local Building Permits Versus Utility Interconnection Approval

Many homeowners mix up these two approvals. They are separate, and you need both.

A local building permit comes from your county or city (Permitting and Inspection for Rooftop Solar). It checks that the racking, roof work and electrical wiring are safe. The utility interconnection approval comes from your electric company.

Watch out: Installing before the utility approves can delay your permission to operate. Delays like these often trace back to equipment and crew scheduling, so review this freight logistics checklist for crews if your install timing has slipped.

Dominion Energy Facility Interconnection Requirements

If Dominion Energy serves your home, its requirements shape what the letter says. Dominion reviews the technical details of your inverter and system size before it approves the connection.

Expect the letter to reference your application number, your service address and the equipment listed in your paperwork. If any of these do not match your install, flag it right away.

Reading the Key Fields in Your Approval Letter

Most articles about interconnection explain the process. Very few explain the letter itself. This section is a field-by-field walkthrough of the document you are actually holding, so you can verify it against your signed contract and your installed equipment before you do anything else. Work through it with a highlighter and a copy of your contract side by side.

Homeowner reviewing a solar interconnection approval letter at a desk
Homeowner reviewing a solar interconnection approval letter at a desk

Project and account identifiers

Look for three identifiers near the top: the utility's application or case number, the customer account number tied to the service address, and the service address itself. The application number is what you will quote in every future call or email, so write it down. The account number should match a recent utility bill. The service address should match the address on your permit and your contract exactly, including directional prefixes, unit numbers, and any difference between a mailing address and the meter address.

Approved system size

The letter will state an approved capacity, usually in kW (DC) or kW (AC), and sometimes both. These are not the same number. DC capacity is the sum of your panels' rated output under standard test conditions; AC capacity is what your inverter can deliver to the grid. A 10 kW DC array paired with an 8 kW inverter may appear as "10 kW DC / 8 kW AC" or only as one of the two.

Export limit and net metering terms

The export limit is the maximum power your system is permitted to push back to the grid, and it may be lower than your system's total capacity. Look for language such as "export limited to X kW" or a reference to a non-export or limited-export control setting. This matters because some approved designs require the inverter to be configured to cap export, and that configuration is a physical setting your installer must apply, it is not automatic.

Equipment details

The letter typically lists the inverter make and model, and sometimes the panel model and count. Compare these against the nameplate on the equipment actually installed, not against the proposal you were quoted. Inverter model substitutions are common when a specified unit is backordered, and a substitution that was never reflected in a revised application can invalidate the approval. Check the model number character by character; manufacturers often ship near-identical models with different suffixes that carry different rated outputs.

Conditions and expiration dates

Approval letters frequently carry conditions, a final electrical inspection, a meter upgrade, a signed interconnection agreement, or proof of insurance, and many carry an expiration date by which the system must be installed or the approval lapses. Find the expiration date and put it on your calendar. If your project timeline is slipping, ask the utility in writing for an extension before the date passes rather than after.

Signature and authorization block

Finally, find the line that states what the letter authorizes. Read the exact wording. Some letters authorize installation only; others authorize connection and operation. That distinction is the subject of the next section, and it is the single most important sentence in the document.

Dominion net metering application: What to Confirm

Net metering credits your bill for power you send to the grid. Confirm your Dominion net metering application lists the correct account and system details. Errors here can delay credits for months.

Compare the net metering terms in the letter with your application. If they differ, call the utility before you proceed.

Solar Permission to Operate and the Solar Interconnection Agreement

Permission to operate, often called PTO, is the utility's written authorization to energize your system and begin exporting power. Your interconnection agreement is the contract that governs how your system connects and operates. They are related but distinct: the agreement is the rulebook, and PTO is the green light. Do not switch on the system until PTO arrives in writing.

Three milestones that are easy to confuse

Most delays and violations trace back to treating one of these as another:

  • Application completeness. The utility has received your application and confirmed it has everything it needs to begin review. This is an acknowledgment, not an approval. Nothing may be installed on the basis of a completeness notice.
  • Approval to install. The utility has reviewed the technical details and authorized you to build the system as described. This is the point at which installation may proceed, subject to your local building permit. It is still not authorization to energize.
  • Permission to operate. The utility has confirmed that the installed system matches the approved design, that required inspections are complete, and that any meter or agreement conditions are satisfied. Only this milestone authorizes you to turn the system on and export power.

A conditional approval sits between the second and third milestones. It typically means the design is acceptable but specific conditions remain outstanding. Read the conditions, assign each one an owner, and do not assume a conditional approval is a PTO.

What usually has to happen between approval to install and PTO

A common sequence is: installation is completed, the local authority having jurisdiction performs a final electrical inspection, the inspection result is submitted to the utility, the utility performs any required meter work or witness test, and the interconnection agreement is executed. Some utilities also require proof of insurance or a signed net metering application before releasing PTO. The order and the specific requirements vary by utility, so treat this as a general pattern rather than a fixed checklist for your project.

Verifying authorization before you turn on the system

Use this checklist before flipping the switch:

  • The letter's approved system size matches your contract and your installed equipment
  • The export limit is stated, and any required inverter export-control setting has been applied and documented
  • Inverter make and model match the installed nameplate
  • Every listed condition is marked complete, with a date and a responsible party

If any box stays unchecked, the system is not yet authorized. A verbal confirmation from an installer or a customer service representative is not a substitute for the written authorization.

Watch out: Energizing before PTO can violate your interconnection agreement, and some utilities treat unauthorized operation as a basis for withdrawing approval or requiring the system to be disconnected until the issue is resolved.

If the letter and the installed system do not match

If the installed inverter, panel count, capacity, export limit, or service address differs from the letter, stop before energizing. Contact your installer first, then the utility, and ask for a revised letter or a formal change to the application. Keep copies of every message. A revised letter is usually faster to obtain before the system is operating than after, because the utility can review the change against the original application rather than investigating an unauthorized installation.

What to Do If Your Letter Details Do Not Match the Installed System

Sometimes the installed system differs from what the letter lists. A different inverter or panel count is a common cause. Do not ignore the gap.

Contact your installer first, then the utility. Ask for a revised letter or a change order. Keep copies of every message you send.

Verifying Authorization Before You Turn On Your System

Use this checklist before flipping the switch:

  • System size matches your contract
  • Export limit is listed and acceptable
  • Inverter details match the installed equipment
  • All approval conditions are marked complete
  • Final inspection passed

If any box stays unchecked, the system is not yet authorized.

Before you energize the system, work through this checklist against your letter and your installed equipment.

Check What to confirm If it fails
System size Matches your contract Contact installer and utility
Export limit Stated and acceptable Do not energize; get clarification
Inverter details Match installed equipment Request revised letter
Approval conditions All marked complete System not yet authorized
Final inspection Passed Schedule and pass before energizing
Permission to operate Received in writing Do not switch on

Frequently Asked Questions

What does a solar interconnection approval letter mean?

A solar interconnection approval letter is written by your serving utility, not your city or county. It confirms that the utility has reviewed your interconnection application and accepted the proposed system to connect to the electric grid under stated conditions. It is typically tied to the project's technical parameters, such as system capacity, inverter specifications, and export limits. The letter does not by itself mean the system may be energized. Read the conditions carefully and confirm whether the utility has also issued permission to operate.

Is an interconnection approval letter the same as permission to operate?

No. An interconnection approval letter typically authorizes the design and connection of the system, while permission to operate, sometimes called PTO, is the utility's final authorization to energize the system and begin exporting power. Many homeowners assume that approval means they can turn on their panels, but utilities usually require a final inspection and their own confirmation first. Check the letter for a required next step before energizing anything.

What should I do if my solar approval letter has incorrect system details?

Contact your installer and the utility's interconnection contact promptly, before the system is installed or energized. Provide the installed equipment specifications, including panel count, system capacity in kilowatts, and inverter model, and ask whether the utility must issue a revised approval. Keep written records of every correspondence. Installing or operating a system that does not match the approved parameters can delay permission to operate.

How long does solar interconnection approval take?

Timelines vary by utility, application completeness, and whether a technical study is required. Incomplete applications, missing documentation, and system design changes are common causes of delay. Track your application status with the installer and the utility, and respond quickly to any requests for information. Asking the utility for its current review timeline at the time of submission can help you plan the installation schedule realistically.